Decision details

B4113 Longford Road Corridor Improvements

Decision Maker: Portfolio Holder for Transport and Planning

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

The scheme is to:
• Create a continuous high quality cycle route from Bayton Rd Ind Est access to Longford. Rd/B4114 roundabout to provide a critical link in the Nuneaton to Coventry cycle way.
• Upgrade the signal junction at Longford Rd/Bayton Rd, including toucan crossing facilities.
• Upgrade the signal junction at Blackhorse Rd junction, including toucan facilities.
• Widening of Longford Rd between Bayton Rd to Longford Rd roundabout
• Tie in to committed S278 Longford Rd roundabout improvement (highway works and cycle facilities)

Decisions:

Resolved

 

That the Portfolio Holder for Finance & Property (Deputy Leader)

 

1)    authorises the addition of the B4113 Longford Road Corridor Improvement Scheme - Phase 1 to the Capital Programme for the value of £1.474 million; and

 

2)    authorises the Executive Director for Communities to procure the necessary construction contract and enter into any such contract and any associated agreements on terms and conditions acceptable to the Executive Director for Resources.

 

Report author: Tasnim Nour

Publication date: 18/03/2025

Date of decision: 14/03/2025

Decided at meeting: 14/03/2025 - Portfolio Holder Decisions/Leader Decisions

Accompanying Documents: