Mark Ryder,
Executive Director for Communities presented this item, which gave
a retrospective summary of the Council’s
performance at the end of Quarter 1 (April - June 2023) against the
strategic priorities and areas of focus set out in the Council Plan
2022-2027. Key sections of the report focussed on:
- Performance against the Performance Management
Framework
- Progress on the Integrated Delivery Plan
- Management of Finance
- Management of Risk
In
presenting the report, Mark Ryder referred members to the
appendices which set out the ‘RAG’ rating of
performance against target. He reminded that this was the first
quarter report and highlighted the areas on track and those where
performance was at risk or not predicted to achieve the target or
measure. Additional information and narrative was provided on
individual schemes.
Scott Tompkins referred to the finance aspects of the report and
a £3.4million projected overspend. Most of this related to
home to school transport and was due to additional service demand
from students entitled to free school transport, an increase in
services for SEND students and inflationary increases. There was a
member working group and an improvement project looking at this
area. Scott gave a performance summary focussing on those areas
where performance was at risk or not predicted to achieve the
target or measure. Additional information was provided for each
area, specifically around home to school transport, flood risk
mitigation and associated works. He highlighted the good
performance on highway maintenance contracts with 100% of targets
being achieved. He emphasised the supporting key performance
indicators which were being achieved consistently by the
contractor, Balfour Beatty, in a contract delivered across
Warwickshire, Solihull and Coventry. It was subject to close
scrutiny by a Highways Maintenance Board which included the
portfolio holders of each authority. This service was in the top
ten nationally in terms of performance. Tree planting was also
highlighted, particularly the need to accelerate tree planting to
hit the required target of planting one tree for every resident in
Warwickshire.
Discussion took place and questions were submitted as
follows:
- The delays in Section 278 developer funded schemes was
discussed. Scott Tompkins explained that as soon as the agreement
was concluded it was added to the capital programme, but the
developer may not complete the scheme for some time, so it showed
as a delay. Scott outlined some of the factors which could
contribute. In essence this provided a forecast of monies being
received that would be spent on schemes. He provided context of the
excellent performance for the previous year on the capital
programme expenditure and forecast to outturn.
- There were concerns about cuts to the Trading Standards budgets
which a member linked to increases in complaints. Members became
aware of illegal activity within their divisions, but the service
had limited responsive capacity. Comment was sought on the increase
in complaint levels, which Scott Tompkins offered to research and a
written briefing would be circulated to members. He drew comparison
to the significant budget cuts which some local authorities had
needed to make to their trading standards services. Warwickshire
had managed to maintain its services for a variety of reasons,
including the calibration service for fuel pumps, used by many
airports. Mark Ryder confirmed that it was an intelligence-led
service which focussed on priority areas. He reminded of the
historic service areas of Trading Standards and gave examples of
the priorities which were now a focus. He had visited the
calibration service earlier in the day and this brought in revenue
from around the world.
- For the Adult Community Learning Service, there was a decline in
income, and this had been the case for the last three quarters.
Mark Ryder confirmed this was reported to the Committee but rested
within the Education Service. An action was taken to investigate
this and provide a report back to members.
- Further discussion about Section 278 (highway) agreements, and
Section 106 (planning gain) agreements. It was noted that there
could be a lengthy period between when agreements were negotiated
and the schemes provided, so was questioned if inflationary costs
impacted on the authority or the developer. Scott Tompkins
confirmed that there was no opportunity to revisit the sums
negotiated through Section 106 agreements. However, for the Section
278 works, the developer paid some monies in advance and then paid
a final bill based on the actual costs charged.
- The Chair raised the Transforming Nuneaton scheme and delays,
referring to the Bermuda Bridge, its ongoing delivery problems and
set out his concerns about delays to works that were scheduled or
planned. The delays seemed to be impacting on other schemes which
Nuneaton needed desperately. The plans to redevelop Vicarage Street
had not been finalised and he quoted other examples about
developing the library and business centre. There seemed to be a
pattern that impacted on the delivery of many of the
schemes.
- Mark Ryder responded, reminding members of the challenges to
purchase commercial buildings and then clear the Vicarage Street
site. This was progressing but was coupled with a period of massive
inflation. This had an impact on delivery of the wellbeing business
centre, which remained a commitment. There had been legitimate
delays. On Bermuda Connectivity, the bridge scheme was coming to a
conclusion, with weekly briefings being provided to members. Mark
and Scott Tompkins touched on the significant challenges faced with
this scheme, the delays experienced and impacts that it had caused
for other projects.
- The Chair appreciated the update, also noting that other
projects had been impacted, including the Hospital and College
Street Island. There appeared a lack of movement to get these
schemes back on track and he asked what options there were to align
these schemes with the other delivery schedules. Mark Ryder
responded that through the Transforming Nuneaton Programme Board
members had the opportunity to see the updates and to provide a
challenge.
The Committee noted the delays
reported and was concerned to see those delays. The Chair was sure
these concerns would be fed back to the Cabinet and Portfolio
Holder, to ensure the Committee’s comments were
heard.