2021-22 Financial Monitoring - Forecast position as at Quarter 2

26/11/2021 - 2021-22 Financial Monitoring - Forecast position as at Quarter 2

Resolved:

 

That Cabinet:

 

1.     Notes the adjusted forecast underspend of £0.114m that would contribute to the Directorate and General Risk Reserves at the end of 2021/22.

2.     Notes the forecast under-delivery of the 2021/22 savings requirement to the value of £0.726m.

3.     Notes the forecast capital spend for 2021/22 of £168.424m, of which £151.433m is capital payments controllable by the County Council and the balance, of £16.991m, relates to schemes funded by s278 developer contributions where the timing is not directly controllable by the Council.

4.     Approves the carry forward of the reprofiled spend on the capital programme of £15.590m in 2021/22 into future years and notes the carry forward of s278 contributions of £15.871m that is not directly controllable by the Council.