Issue - decisions

Education Capital Programme 2022/23

03/10/2022 - Education Capital Programme 2022/23

That Council agrees to add to the capital programme the scheme delivery of a school at Myton Gardens, at a cost of £13.400 million funded from Department for Education grant.


09/09/2022 - Education Capital Programme 2022/23

That Cabinet:

 

1.     Recommends to Council that £13.400 million be added to the capital programme to deliver the scheme at Myton Gardens, to be funded from Department for Education grant.

2.     Approves the addition to the capital programme of £0.470m funded from developer contributions, Department for Education grant and academy trust contributions to deliver the remaining schemes in section 3 of the report, provided that the release of funding for the scheme at Long Itchington Primary School is subject to confirmation of the remaining funding by the Diocese of Coventry Multi Academy Trust.

3.     Authorises, subject to Council’s agreement to the required addition to the Capital Programme and prior agreement from the Strategic Director for Resources as to whether a project will be school led or not, the Strategic Director for People in consultation with the Portfolio Holder for Finance and Property, to invite tenders and enter into the appropriate contracts or (where the scheme is school led) to make the necessary funding arrangements for these schemes on terms and conditions considered acceptable to the Strategic Director for Resources